Transportation, Fabrication, and Installation of 6 Petroleum Coke Storage Silos
Units 301 and 401
Project Description:
Receiving and transporting materials from the employer’s warehouse, unloading at the installation site, fabrication, assembly and welding (complete installation), testing, sandblasting, and painting of 6 petroleum coke storage silos (tanks) related to Units 301 and 401 at the Carbon Anode Production Site of Amirkabir Carbon Industry (Kheirabad Site).
Names of Silos (Tanks):
-
Unit 301 Tanks:
Two tanks with a diameter of 24 meters
-
Unit 401 Tanks:
Two tanks with a diameter of 16 meters
-
Unit 401 Tanks:
Two tanks with a diameter of 8 meters
Approximate Project Weight:
1,500 tons
Contract Details:
- Contract No.: MCST-301, 401
- Contract Duration: 7 solar months, equivalent to 210 days
- Contract Amount: 948,584,000,000 IRR
Employer:
Amirkabir Carbon Industry Company
Managing Director: Mr. Engineer Ghaffari
Tel: +98 86 33126970
Project Location:
Kheirabad Industrial Town – Amirkabir Carbon Industry Site